The safety operation regulations for loading and unloading crane pipes are a very important link in fluid loading and unloading operations, directly related to the safety production of various chemical units. Nowadays, the loading and unloading crane tube has gradually replaced the original method of connecting hoses to load and unload fluids, which has greatly improved in terms of safety and environmental protection compared to the past.
According to different loading and unloading scenarios, crane pipes can be divided into railway loading and unloading arms (train crane pipes), highway loading and unloading arms (car crane pipes), and marine loading and unloading arms (ship arm, oil arm); According to the loading and unloading position, it can be divided into upper and lower crane pipes; According to the type of medium, the crane tube can be divided into liquefied gas crane tube, LNG low-temperature crane tube, methanol crane tube, liquid ammonia crane tube, nitric acid crane tube, chloromethane crane tube, etc.
Operating procedures for crane tubes before loading and unloading operations:
After receiving the arrival forecast of the oil tank truck, the person in charge of the oil depot arranges relevant personnel to prepare for loading and unloading, and all personnel are in place and dressed according to regulations;
The measuring personnel check the liquid level of the unloading oil tank, and the pump driver checks whether the oil pipeline and oil pump are normal;
Collect a qualified notice of oil and verify whether the unloading type matches the opening of the oil pipeline valve;
Check whether the safety devices of the tank truck comply with regulations;
Ensure that the crane tube and movable ladder are in a reset and locked state.
Operating procedures for crane tubes during loading and unloading operations:
Open the locking mechanism of the inner arm of the crane tube, remove the arm from the hook, and move the arm to the tank mouth or flange, quick connector, or dry valve connection part of the tanker.
Operate the outer arm to drop and fully insert the vertical pipe into the tank opening of the tank car (top open loading and unloading truck), or connect the outer arm to the top or bottom flange or quick connector of the tank car (top or bottom closed loading) or dry valve connection (gasoline and diesel lower loading).
Check for any dripping or leakage;
Clamp the static grounding clamp onto the tanker;
Operating procedures for crane tubes after loading and unloading operations:
Close the pipeline valve system, stop medium transmission, and remain silent for about half a minute to empty the fluid medium in the arm tube;
Slowly pull out the vertical pipe or disconnect the flange, quick connector, or dry valve connection to separate the arm from the tanker;
Reset the crane tube to the inner arm locking device;
Remove the static grounding clamp.
Precautions for operating procedures of crane tubes:
The crane tube can only be opened during loading and unloading operations, and should be in a reset and locked state at other times;
Tank trucks are not allowed to enter or leave the loading and unloading area until the crane tube is reset. The tank truck is strictly prohibited from moving during the loading and unloading operation of the medium.
Contact Us
- High-tech Industrial Development Zone, Zhengzhou, Henan.
- sales@ottimafluid.com、peter@ottimafluid.com
-
+86-13503854331
-
Wechat: +86-13503854331 +86 13938423393
-
Whatsapp: +86-13503854331 +86 13938423393
Safety Operating Regulations for Loading and Unloading loading arm
Apr 13, 2023
You Might Also Like
Send Inquiry